Hong Kong-Zhuhai-Macao Bridge Island Tunnel Project (East Artificial Island)

Category:Steel Structure
Contract content: offshore erection of steel trestle and steel platform (pile driving, support installation, beam production and installation, Bailey frame assembly and installation, bridge deck installation, railing production and installation);
Retail price
0.0
Market price
0.0
Number of views:
1000
Product serial number
Hotline: 86-513-68916098
E-mail: nt@ys-gg.com
Quantity
-
+
Stock:
0
Product description
Parameters
Contract content: offshore erection of steel trestle and steel platform (pile driving, support installation, beam production and installation, Bailey frame assembly and installation, bridge deck installation, railing production and installation);
 
Project scale: 350 meters of steel trestle bridge, 6 steel platforms (total steel structure 2650t, 5600m2), project cost 3.5 million yuan;
 
Commencement and completion date: 2012.10~2013.7.

Bridge construction trestle erection (beret installation)

Bridge construction trestle erection (beret installation)

 

Bridge construction trestle erection (beret installation)

Bridge construction trestle erection (column top beam installation)

 

Bridge construction trestle erection (column top beam installation)

Bridge construction trestle erection (steel platform piling)

 

Bridge construction trestle erection (steel platform piling)

Bridge construction trestle erection (steel platform piling)

 

Bridge construction trestle erection (steel platform piling)

Platform hoisting steel pipe piles

 

Platform hoisting steel pipe piles

Trestle and steel platform railing

 

(2), contract content: continuous box girder steel support offshore erection (piling, support installation, beam production and installation, Bailey frame assembly installation, bridge deck installation, railing production and installation); project scale: offshore piling 263 pieces, steel structure Installation of 6,400t, steel structure demolition of 5800t, project cost 8.15 million yuan; start and completion date: 2013.11~2015.7.

 

Hong Kong-Zhuhai-Macao Bridge Island Tunnel Project (East Artificial Island)

Box girder steel support for supporting piles

 

Box girder steel support tie rod installation

Box girder steel support tie rod installation

 

Box girder steel support tie rod installation

Box girder steel support beam system and sandbox structure installation

 

Box girder steel support Bailey frame system installation

Box girder steel support Bailey frame system installation

 

Box girder steel support Bailey frame system installation

Box girder steel support transverse, longitudinal and scissor support system

 

Box girder steel support transverse, longitudinal and scissor support system

Partial renderings of box girder steel support completed

 

(3). Contract content: manufacturing and installation of steel casing box for pier caps of the bridge section of East Artificial Island (sea cutting piles, casing installation, assembly, and dismantling). Project scale: 6 sets of steel box processing (steel structure 950t), project cost: 9.138 million yuan; start and completion date: 2012.12~2013.9.

 

Hong Kong-Zhuhai-Macao Bridge Island Tunnel Project (East Artificial Island)

Fragment production of steel casing box for caps of bridge section

 

Fragment production of steel casing box for caps of bridge section

Assembling drawing of steel case for caps of bridge section in factory

 

Assembling drawing of steel case for caps of bridge section in factory

Assembling drawing of steel casing box for caps of bridge section

 

Assembling drawing of steel casing box for caps of bridge section

Sea transportation of steel box for beam caps

 

(4) Contract content: processing of large formwork trolleys for the anti-wave wall of the east artificial island and the partition wall of the open section of the tunnel. Project scale: 7 sets of processing trolleys, total steel structure processing 240t; project cost 2.57 million yuan; start and completion date: 2014.10~2014.12.

 

Sea transportation of steel box for beam caps

Assembly drawing of the workshop in the trolley factory

 

Assembly drawing of the workshop in the trolley factory

On-site construction drawing of wave wall trolley

 

On-site construction drawing of wave wall trolley

Trolley construction drawing for the open section of the tunnel entrance

 

Trolley construction drawing for the open section of the tunnel entrance

Trolley construction drawing for the open section of the tunnel entrance

Keyword:
island
steel
installation
the
bridge
support
Scan the QR code to read on your phone
We could not find any corresponding parameters, please add them to the properties table

More works

 Fabrication and Installation of Large Steel Cofferdam for Pier 26 of Zhaohua Bridge, Xiangtan, Hunan
Fabrication and Installation of Large Steel Cofferdam for Pier 26 of Zhaohua Bridge, Xiangtan, Hunan
Fabrication and Installation of Large Steel Cofferdam for Pier 26 of Zhaohua Bridge, Xiangtan, Hunan
 Jiangsu Dongtai Wind Farm Test Pile and High Pile Cap Project Dongtai Offshore Wind Power
Jiangsu Dongtai Wind Farm Test Pile and High Pile Cap Project Dongtai Offshore Wind Power
High pile cap steel box production, transportation, on-site installation (sea piling, box installation), production and installation of ship components, J-tube production and installation.
 Jiangsu Rudong Offshore Wind Power Installation
Jiangsu Rudong Offshore Wind Power Installation
Jiangsu Rudong Offshore Wind Power Installation
 Donghai Bridge Project
Donghai Bridge Project
Fabrication and on-site installation of steel box for the foundation of bridge pier caps (pile cutting at sea, box installation, assembly, and removal).
 Hebei Tangshan Leting Offshore Wind Power Project
Hebei Tangshan Leting Offshore Wind Power Project
Production and transportation of steel box for supporting platform, installation of steel box on site (pile cutting at sea, installation, assembly and removal of box).
 Shanghai Lingang Offshore Wind Power Phase II Project
Shanghai Lingang Offshore Wind Power Phase II Project
Contract content: production and transportation of steel casing for supporting platform, installation of steel casing on site (pile cutting at sea, installation of casing, assembling and dismantling).
 Xiangshui Offshore Wind Power Project
Xiangshui Offshore Wind Power Project
Production and transportation of steel box and jacket for supporting platform. Project scale: 37 sets of steel box processing, 3 sets of jacket processing (steel structure processing volume)
 Hong Kong-Zhuhai-Macao Bridge Island Tunnel Project (East Artificial Island)
Hong Kong-Zhuhai-Macao Bridge Island Tunnel Project (East Artificial Island)
Contract content: offshore erection of steel trestle and steel platform (pile driving, support installation, beam production and installation, Bailey frame assembly and installation, bridge deck installation, railing production and installation);
 Zhijiang Bridge Project of Zhejiang Hangxinjing Expressway Extension
Zhijiang Bridge Project of Zhejiang Hangxinjing Expressway Extension
6. Design and manufacture of large steel caisson for the bearing platform of No. 7 pier, and design and manufacture of special triangular hanging basket for 6-meter span.

Product Inquiry

留言应用名称:
产品留言
描述:

产品留言

验证码

Service Hotline::

86-513-68916098

Address: Yaosheng Road, Pingchao Town, Tongzhou District, Nantong City, Jiangsu Province

Fax:86-513-68916085

Email:nt@ys-gg.com

Copyright ©  2015 Nantong Yaosheng Steel Co., Ltd.  All rights reserved.     苏ICP备11028791号